Lawrence & Kansas Civic ReportsHomeWhy Kansas power projects waitKansas peak power demandHome energy costs in Douglas CountyData centers and Kansas home electric billsIs Lawrence's new building code adding homes?How Lawrence fixes streets and pipesAll amendmentsTransit report
Kansas grid connection queue

Why Kansas power projects wait, and why most never get built

Made by AI agents, with a person directing and checking the work. How this was made.

Last amended: 2026-10-25. See all amendments.

A neutral look at Kansas requests in the Southwest Power Pool (SPP) generator interconnection queue. Data through October 22, 2026.

The short version

Horizontal bar chart of Kansas requested capacity by technology, split into built, active, suspended and withdrawn; withdrawn dominates for wind and solar.
Most requested capacity in Kansas has been withdrawn, not built. Source: LBNL Queued Up (through 2025).

1. What the queue is

Before a power plant can connect to the high-voltage grid, the grid operator studies whether the grid can carry its power and what upgrades are needed, and who pays. The waiting list for those studies is the "interconnection queue." In Kansas the operator is SPP. Projects pass through study stages (in SPP: DISIS cluster study, facility study), sign an interconnection agreement (IA), then must still finance and build.

2. Who it affects

Stacked bars by request year showing Kansas capacity requested and its current status.
Requests surged after 2016; most later requests were withdrawn or are still waiting. Source: LBNL Queued Up.

3. Where projects stall

Early exits. 110 of the 258 Kansas withdrawals with dates left within a year, typical of speculative or "placeholder" requests that drop out once study costs appear. The 2023 wave is striking: 63 Kansas requests filed in 2023 (about 14.3 GW) withdrew, typically within six months [2].

Late exits. 80 withdrew after three or more years in the queue, after paying for studies, which usually signals that upgrade costs, financing or buyers for the power did not line up. The data cannot tell us which.

Bar chart of Kansas withdrawals by years in queue before withdrawing.
Many projects withdraw after years of study. Reasons are not public; timing is a proxy. Source: LBNL Queued Up.

After the agreement. The newest stall point is after the IA is signed. SPP's live list shows 67 Kansas projects with a fully executed IA that are not yet operating, mostly solar (27), batteries (17) and wind (16); 4 of the 67 are on formal suspension, and 2 are fast-tracked ERAS gas plants signed in 2025-26 [1]. SPP's "Cause of Delay" field gives no Kansas-specific reason [1].

Dot plot of Kansas projects not yet operating, by years since request, split into signed-agreement and still-in-study groups.
Many Kansas projects with signed agreements filed 5-7 years ago are still not built. Source: SPP live queue CSV (10/22/2026).
Bar chart comparing median years from request to agreement, to operation, and to withdrawal, Kansas vs all SPP.
Median elapsed years between milestones. Source: LBNL Queued Up (through 2025).

4. Where in Kansas

Two Kansas county maps: built capacity concentrated in a few western and central counties; withdrawn capacity spread widely.
Where Kansas projects were built versus withdrawn. Source: LBNL Queued Up (county as reported); Census county boundaries.

See the county map and tables for every county.

5. Options being discussed, as scenarios

These are illustrative scenarios, not recommendations. Costs are rough. See Scenarios for the full table.

Scenario Rough cost Who benefits Who pays / trade-off
A. Status quo plus FERC Order 2023 rules (cluster studies, firmer deadlines, higher deposits) [6] Administrative; already in place Ready projects get studied faster Smaller developers face higher deposits
B. Fast-track for resource adequacy (SPP's ERAS) [5][7] Studies paid by applicants; one-time window Utilities needing capacity by ~2030; 9 Kansas ERAS requests, ~3,100 MW, about 70% gas-fired [1][5] Projects already waiting in the regular queue; open-access concerns raised at FERC [7]
C. Build transmission ahead of generators (JTIQ-style) [3][4] JTIQ: ~$1.65B capital for ~28.6 GW enabled (about $58 per kW); roughly 11.5%/yr carrying charge; $464.5M federal grant [3][4] Many projects share one upgrade instead of each paying alone Generators pay per-MW charges; risk of under-used lines
D. Help signed-but-unbuilt projects finish or exit (milestone enforcement, reuse of capacity) Low (rules) Projects behind them in line Developers holding positions
E. Reuse grid connections at retiring plants ("surplus/replacement interconnection") Low to moderate Faster, cheaper hookups Limited to specific sites

6. Limits

How this was made

Data were downloaded from the public sources listed on the sources page, processed with open scripts, and checked by an automated guardrail script (blanks, control totals, provenance, history freshness, and an external reality check against LBNL's own published SPP totals). See Methods.